Finally,
the public relation carrot circulated by the Railway authorities for the last
one year regarding the completion of the Lumding – Silchar broad gauge
conversion project by the end of 2013 seems to have ended. NF Railway’s General
Manager Mr. RS Virdi has recently expressed “concerns” about the possibility of
gifting the broad gauge line as a new year present to the people of Barak
Valley in 2014.
The picturesque Silchar - Lumding Metre Gauge Corridor, Photo Courtesy: IRFCA |
Indeed,
the project, riddled with elephantine problems, seems to have become one
mammoth of a challenge for the Indian Railways, for which they do not seem to
have any ready solution. For the first decade since the launch of the project
in 1996, the railway officials kept citing the law and order situation in NC
Hills (now Dima Hasao) as the main impediment towards the slow progress of the
conversion work. However, in the last couple of years the situation has
improved in the hills after a cease fire agreement between the terror group
Dima Halam Daoga (DHD – Black Widow) and the government of Assam.
The
progress of work has gained some momentum now but it is still far slower than
the desirable requirement. Now the railway authorities and their contractors
are showing other reasons for the delay in finishing the project such as
inclement weather, unexpected geotechnical hazards, slide prone and loose
nature of the Borail hills and so on. But the question is, in this era of high
technical and engineering expertise, when railway corridors are being
constructed in far more difficult terrains such as Kashmir and Tibet, why these
apparently ‘new’ reasons are being brought to light a good 16 years after the
beginning of work?
If
these unexpected factors are emerging one after another now, there is a huge
possibility that the pre construction surveys related to soil condition,
presence of gases, weather behaviour etc were not conducted properly.
In
the month of May, a nine member delegation of the ‘Silchar – Lumding Boad Gauge
Rupayan Sangram Committee’ went on a tour of the under-construction corridor to
assess the ground condition. In course
of the tour, they found that many areas in Barak Valley which had never faced
any issues related to law and order, had also not seen much progress in
construction work, which completely defeats the government’s claim that
unstable law and order was the main reason for the delay in finishing the
project on time.
Mr.
Nirmalya Das, a member of this delegation, mentioned in a very well written
article that appeared recently in the Bengali daily ‘Samayik Prasanga’ that the
all important Barak bridge has still not been completed and very little work
has happened in other nearby areas such as Sukritipur and Damcherra. He further
said that out of the 17 tunnels on the stretch, only 10 had been completed.
Tunnel number 10, on this stretch has
been in news in the recent times for its slow progress and the emission of
methane gas from the hills, but along with this tunnel, the 7th and
12th tunnels are also major reasons for concern.
On
any new railway corridor, trial runs have to carried out for a few months, to
check the fitness of the tracks before opening the same for the public. The
Commissioner of Railway Safety (CRS) also has to certify the entire corridor
before passenger and goods trains start plying. So, when construction work it
self is far behind schedule, how will the railway carry out the trials, and
open it by the beginning of 2014?
A
progress report uploaded on NF Railway’s construction related website, shows
that apart from parameters such as land acquisition, station buildings, railway
over bridges and to an extent, the minor bridges, work in all other departments
is in progress. Out of the superstructures of 83 major bridges, only 58 have
been completed. 10,745 Rm of tunnels
have to be constructed, out of which only 7,042.45 Rm have been completed. So,
if this is the progress of work in 16 years, how can the remaining work be
completed in less than another two years?
Mr.
Das has also observed in his article that, the quality of sand (mixed with
soil) being used for the construction of the tunnels is so poor that we would
not even use them for constructing our houses. When the site engineer was
questioned by the delegation regarding the same, he claimed that the sand was
being ‘rectified’ before use and had already been cleared by the railways.
Huge
aspersions have already been raised regarding the quality of work on this
stretch. The 201 km long Lumding - Silchar hill section passes through
treacherous terrain which neither have good roads, nor very high quality urban
settlements. Therefore, it is not very easy for the railway officials to
frequently inspect the progress of work. Just imagine, if a contractor
compromises on building materials while constructing a bridge near a remote
railway station such as Ditakcherra, how would any senior official sitting at
Lumding or Maligaon know? But if indeed the quality of work is poor, the people
of Barak Valley might have to pay a very heavy price for it in the future.
In
our last article on the same topic titled, “Lumding To Silchar: The Story of an
Endless Tunnel” uploaded in January, 2011, we had mentioned how the British
could conceive, plan, construct and commission the entire stretch in about 20
years more that a hundred years back, when there was no technology and definitely
no roads and other infrastructure. Now about a hundred and ten years later, we
cannot even convert a metre gauge line into broad gauge in almost the same time
frame. Its indeed a colossal shame on our existence as an independent nation
and claims as a potential world power!
Lumding - Silchar Broad Gauge project will not be completed by 2014. The NF railway officials knows the huge pending work of the project and instructions they are getting from dispur to delay the work.
ReplyDeletePeople of barak valley are wasting time on Rumi Nath episode. They forget the main issue of barak balley - The Lumding-Silchar Broad Gauge project. They should come out of their comfort zone and raise voice against the idiots who are deliberately delaying the project work for their personal gains.
Thanks
Team Silchartoday
www.silchartoday.com
Anonymus : March 25, 2013
ReplyDeleteDiversion from the Northeast Projects Funds has been reported. But there was no protests from Dispur bosses. They do not know how to fight & raise voice against the step-motherly attitude of the Sonia-Manmohan Brigade toward the state. They have only learnt to comply with the instruction from Delhi for their personal gains.
There are 14 elected MPs from Assam & they make big(but false) promises before the elections. But when they go to Delhi, they become dumb. In Delhi, the MPs of southern states always remain busy in meeting the ministers for sanction of various projects for their state & they succeed. Our MPs sleep when they are in Delhi. Two more election will go but Lumding Silchar BG Conversion will not see the light of the day.